National Children’s Hospital ‘held hostage’ in negotiations with BAM, health committee hears

National Children’s Hospital ‘held hostage’ in negotiations with BAM, health committee hears

David Gunning of the National Paediatric Development Board told the Oireachtas health committee he could not say the June 2025 timeline will be met without that level of detailed report from the builders BAM.

“We need a detailed programme which we can analyse and scrutinise.”

Another slip in the timeline is not impossible, he added.

He added that “as of today not one room has been fully completed”.

Some 3,100 rooms including theatres have yet to be signed off as complete.

Earlier, the officials said there is the potential to finally be completed by next June, or around that time, if BAM delivered in how it was resourcing the job.

Amid accusations that the builders BAM were holding the hospital as “hostage” to extract more money, with additional claims of over €700m, it also emerged that some signs of progress in speeding up the final stages of the long-delayed hospital were seen last week.

The meeting heard that 72 rooms were re-offered last week and they are being inspected.

Phelim Devine, the project director, told the committee that the key problem is that none of the rooms are completed to a standard with significant unfinished sections.

“We are averaging about 13 to 15 defects per room, on average. These aren’t scuffs of paints. These are compliance issues. It is remarkable that we have these rooms offered as complete when in fact they are not complete.”

Mr Gunning said that “hundreds of rooms” fully completed need to be offered to meet the June timeline.

The builders have only committed to around 60pc of the resources needed to complete the programme so far.

He also said that even if the hospital is finished by June it will not open to the first patients until 2026.

He told the committee “BAM’s continued failure to provide a compliant baseline programme and its shifting of dates is not acceptable to the the board”.

He accused the builder of a “a complete disregard for internationally recognised professional processes”.

The project “should be working like a factory, spitting out rooms” , he added.

Mr Gunning accused BAM of using the hospital as a “hostage” to secure more funding from the State.

BAM is claiming an additional €748m and 18 claims make up 80pc .

While Bam has claimed this value – to date, the net change to the overall contract sum – as determined by the Employer’s Representative (ER), agreed in conciliation and subject to an adjudication decision – is approximately €35 m, excluding inflation, he added.

The board said the number of additional days of work it believes it needs to pay for is fewer than 20 but BAM is claiming more than 700.

A process of assessment is available and number are in the courts.

Mr Gunning rejected accusations by the builders that 23,000 design changes was behind the delay.

Mr Devine disputed how changes were defined, and said that there have only been 449 change orders, adding that many of the changes BAM describes could have been minor updates to drawings.

Source link

Related Articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Stay Connected

0FansLike
0FollowersFollow
0SubscribersSubscribe
- Advertisement -spot_img

Latest Articles